Building permits

Building permit is issued by municipality administrations when special request is given. The same authority then loads the project into Lithuanian Republic building permits and maintenance information system online - www.planuojustatyti.lt where State institutions which are responsible for project requirements compliance are indicates. Currently there are 16 different institutions according to Lithuanian Republic building laws in charge of project compliance. The suggestion here is to entrust the designer to deal with this task as the building permit issuance is tricky and complicated process. The duration in order to receive the permit is up to 20 days for non-special construction type buildings (STR 1.01.07:2002) and up to 35 days for special project type buildings (STR 1.01.06:2002).

For your convenience with signed power of attorney we can get technical conditions’ documents, cooperate with institutions, get building permits and other required forms concerning the project documentation.